One important verification point to check when defining a plan, is whether the content load is achievable.
The new plan load can be compared to the data presented in the Planning ‘#Trends’ view.

Viewing the ‘Scores chart’ and ‘Story points chart’, the user will be able to assess the actual average number of story points that are completed across the historical trend. If this actual average is significantly below the content story points scheduled for the new plan, then it would be prudent to reduce the task content to a more realistic level.